Complete Mining Fleet Delivered to 4,000m Elevation
Задача
Delivering 23 pieces of heavy mining equipment to a mine at 4,000 meters elevation presented unique challenges: high-altitude road conditions, extreme weather windows, oversized dimensions requiring road modifications, and the need to coordinate with ongoing mine operations.
Наше решение
We coordinated pickup from the manufacturer's facility and transported equipment to Port of Baltimore via specialized heavy-haul trucks. RoRo vessels carried the equipment to Chile, where our local team managed customs and inland transport through mountain roads to the mine site.
Хронология проекта
Pickup & Prep
3 weeksCollect from manufacturer, USDA wash, staging
US Transport
2 weeksHeavy haul to Port of Baltimore
Ocean Transit
4 weeksRoRo vessel to San Antonio, Chile
Inland Delivery
6 weeksCustoms, mountain transport to mine
Использованное оборудование
Результаты
- All 23 units delivered within 5-month window
- Zero equipment damage despite challenging terrain
- Mine commissioning proceeded on schedule
- Cost-effective RoRo solution vs. breakbulk alternatives