45 Units of Heavy Equipment to Sydney Metro Project
Various US LocationsSydney, Australia
45
Equipment Units
8 cities
Origins
1,800 MT
Total Weight
100%
Biosecurity Clearance
Задача
The client needed to mobilize 45 pieces of construction equipment from 8 different US locations to Sydney for a major metro rail project. Australian biosecurity requirements demanded thorough cleaning and inspection of all equipment.
Наше решение
We consolidated equipment from across the US to Port of Baltimore, where each unit underwent USDA washing and biosecurity preparation. RoRo vessels transported the fleet to Sydney, where our Australian partner managed customs and delivery to the project site.
Хронология проекта
1
Collection
4 weeksPickup from 8 US locations
2
Preparation
2 weeksUSDA wash and biosecurity prep
3
Ocean Transit
5 weeksRoRo voyage to Sydney
4
Australian Delivery
3 weeksCustoms, inspection, site delivery
Использованное оборудование
Step-deck and lowboy trailers
RoRo vessels
USDA certified wash facilities
Biosecurity inspection stations
Результаты
- All equipment passed Australian biosecurity on first inspection
- Consolidated shipping reduced per-unit costs by 20%
- Metro project broke ground on schedule
- Ongoing support contract for additional phases