Skip to main content
+1 (888) 996-7619|18+ Years of Excellence|

Track-type tractor (dozer) · Caterpillar

How to ship a CAT D8 overseas

From our loading records for the CAT D8L, the CAT D8 usually goes in 1 × 40 ft open top + 4 × 40 ft high cube. At 87,100 lb (39,500 kg), the CAT D8 is heavier than a 40 ft flat rack carries (about 86,000 lb / 39,000 kg), so it ships whole RoRo where a lane serves your destination, or breakbulk where none does. It can also be containerized after major disassembly (blade off, ripper off, cab or ROPS removed and crated, and track chains and shoes off), across at least 2 containers by weight; we survey it first and quote both.

Loaded by Seaway

How we load the CAT D8

Our loading records list earlier and sister models of the CAT D8 (CAT D8L, CAT D8H, CAT D8K, CAT D8N, CAT D8R). The usual plan is 1 × 40 ft open top + 4 × 40 ft high cube; we confirm it for your machine's year and options before booking.

  • 1 × 40 ft open top + 4 × 40 ft high cubeOr: 1 × 40 ft open top
  • Loads with the standard preparation: fluids checked, battery isolated, machine cleaned and lashed.
40' open top container · Isometric viewDoor end of the 40' open top container, left half closed, right half cut through the door opening: door opening 7 ft 8 in (2.34 m) wide and 7 ft 6 in (2.28 m) high, inside height 7 ft 10 in (2.38 m). Cargo too tall for the door loads by crane through the roof.MAIN MACHINELOAD THROUGHTHE ROOF39 ft 6 in12.03 m40' open top containerISOMETRIC VIEW · SEAWAY PROJECT CARGO
1 × 40 ft open top: main machine
40' high cube container · Isometric viewDoor end of the 40' high cube container, left half closed, right half cut through the door opening: inside width 7 ft 8 in (2.34 m), inside height 8 ft 10 in (2.7 m), door opening 7 ft 8 in (2.34 m) wide and 8 ft 6 in (2.6 m) high.DISMANTLEDPARTS39 ft 6 in12.03 m40' high cube containerISOMETRIC VIEW · SEAWAY PROJECT CARGO
4 × 40 ft high cube: dismantled parts

From our dismantling and loading records, checked July 2026. Your machine's year, attachments and options can change the boxes; we confirm before booking.

CAT D8 shipping dimensions

Weight
87,100 lb (39,500 kg)operating weight
Machine type
Track-type tractor (dozer)
Transport length
25 ft 11 in (7.91 m)
Transport width
9 ft 2 in (2.79 m)
Transport height
11 ft 7 in (3.53 m)
Configuration
Shipping weight 76,100 lb (34,530 kg). Length includes SU blade and single-shank ripper; SU blade 13 ft 3 in (4.04 m) wide, so the blade ships separately.

Published figures for the configuration shown. Shoes, tyres, buckets, counterweights and options change them, so we confirm the dimensions on your machine before booking.

Every way to ship a CAT D8, best first

Worked out from the dimensions above against container, flat rack and RoRo limits. RoRo depends on a regular sailing to your port.

#Best methodFitPreparation
1RoRoBest fitWhere a RoRo lane serves the destinationDrives on assembled where a RoRo lane serves the destination.
240 ft high-cube containerAfter major disassembly, across containersTaken apart and loaded across at least 2 40 ft containers by weight, with open-tops for tall pieces: blade off, ripper off, cab or ROPS removed and crated, and track chains and shoes off. We survey the machine first and quote this next to shipping it whole. How we containerize
3BreakbulkFits as isLifted aboard by crane as breakbulk; used when no flat rack or RoRo option suits the port.

Containerizing a machine means taking off the parts that stop it fitting, then crating, labelling and lashing them in the same box. See how we containerize heavy equipment

Container, flat rack, RoRo or breakbulk?

We quote in this order because it is usually cheapest first. Most machines that look too big for a box fit once our crew takes off the bucket, boom, cab or wheels; larger ones are taken further apart across several containers, and pieces too big or heavy for a flat rack or roll trailer go breakbulk.

01Container

Work needed
We partially disassemble when needed (bucket, boom, cab, wheels), or take larger machines further apart across several high-cubes and open-tops, then crate, block and lash every part.
Destinations
Widest: almost every port worldwide, plus inland delivery by rail.
Typical cost
Usually the lowest, with no out-of-gauge surcharges.
Protection
Sealed steel box; loose parts and attachments travel locked inside.
Best for
Most machines: compact ones as they are, others after partial disassembly, and large ones split across several containers.

02Flat rack

Work needed
Ships assembled, blocked and lashed. Surcharges apply when wider than 2.4 m or taller than about 1.95 m.
Destinations
Most container ports, on the same vessels as containers.
Typical cost
Moderate; rises with every centimetre out of gauge.
Protection
Open to the weather; we protect cabs, electronics and hydraulics.
Best for
Excavators, dozers and loaders too wide for a container door.

03RoRo

Best fit
Work needed
Drives on assembled; non-runners go on a roll trailer.
Destinations
Fewer destinations: regular lanes to Europe, West Africa, the Middle East, Oceania and parts of Latin America.
Typical cost
Often competitive for large self-propelled machines where a lane exists.
Protection
Below deck, but loose items and attachments cannot ride inside the cab.
Best for
Running machines going to a port with regular RoRo sailings.

04Breakbulk

Work needed
Lifted aboard piece by piece by ship’s or shore cranes, on its own skids or cradle, then stowed and lashed in the hold or on deck.
Destinations
Ports with breakbulk berths and heavy-lift cranes; sailings are booked voyage by voyage.
Typical cost
Usually the highest for a single small machine; often the only option for the largest pieces.
Protection
In the hold or lashed on deck; we crate, wrap and protect exposed parts.
Best for
Pieces too large or heavy for a flat rack or roll trailer: transformers, process modules, mining trucks, crane sections.

Preparing a CAT D8 for export

  • Tier 4 Final and Stage V engines need ultra-low-sulfur diesel (15 ppm or less) and DEF. Where only high-sulfur diesel is sold, the after-treatment clogs, so check fuel quality or source a lower-tier export machine.
  • Telematics (such as Cat Product Link, Komtrax or JDLink) may stop working abroad; the dealer can transfer or end the subscription before export.
  • D8 and larger dozers ship with the blade and ripper removed to stay within flat rack width; we crate the pins and hardware with the machine.

Where machines like the CAT D8 go

CAT D8 shipping questions

Does a CAT D8 fit in a shipping container?

From our loading records for the CAT D8L, the CAT D8 usually goes in 1 × 40 ft open top + 4 × 40 ft high cube. At 87,100 lb (39,500 kg), the CAT D8 is heavier than a 40 ft flat rack carries (about 86,000 lb / 39,000 kg), so it ships whole RoRo where a lane serves your destination, or breakbulk where none does. It can also be containerized after major disassembly (blade off, ripper off, cab or ROPS removed and crated, and track chains and shoes off), across at least 2 containers by weight; we survey it first and quote both.

How much does a CAT D8 weigh for shipping?

Caterpillar lists the CAT D8 at 87,100 lb (39,500 kg) (operating weight). Attachments, counterweight options and fuel change the figure, so the weight on the bill of lading comes from the machine itself.

What are the shipping dimensions of a CAT D8?

25 ft 11 in × 9 ft 2 in × 11 ft 7 in (7.91 × 2.79 × 3.53 m) (length × width × height) in transport position, from Caterpillar's published specifications. Shoes, tyres and options change them, so we check before booking.

What has to come off a CAT D8 to ship it?

To containerize it: blade off, ripper off, cab or ROPS removed and crated, and track chains and shoes off. Our crew does the work, crates and labels every part, and loads the pieces across at least 2 containers, with documentation for reassembly. Shipped whole on a flat rack or RoRo, it needs little or no disassembly.

Can a CAT D8 ship RoRo?

Yes, where a RoRo lane serves your destination port. It drives on under its own power. RoRo from the U.S. reaches fewer countries than containers and flat racks, so we check your port first.